Nell M. Hurley
OF COUNSEL
Practice Areas:
- Construction Law, Construction Contracts, Construction Claims
- Commercial Litigation
- Surety Law, including Payment and Performance Bonds
- Lien Law, including Construction Liens
Education:
- Albany Law School of Union University, J.D. 1984
- St. Lawrence University, B.A. with Honors 1981
Nell M. Hurley, Of Counsel, has many years of experience representing contractors, owners, construction managers, sureties, and other related entities. Her practice has included all aspects of contract review and negotiation, all phases of state and federal court litigation, including analysis of claims, preparation of pleadings, document discovery and depositions, motions, settlement negotiations, trial preparation and appeals, and alternative dispute resolution including arbitration and mediation.
Substantive areas of interest and experience for Nell include bid protests, Labor Law and prevailing wage, performance and payment bond claims and defaults, liquidated damages and no damages for delay clauses, limitations defenses, breach of warranty/guaranty, termination, acceleration, change orders and extra work, indemnification, mechanic’s liens, and statutory trust funds,
Nell was lead attorney on a 40 million dollar dispute with the New York State Power Authority involving construction of a hydroelectric power plant near Albany, New York; litigated a 2 million dollar case in Federal Court concerning a wastewater treatment facility in Dutchess County, New York; prepared and argued appeals involving enforcement of a public owner’s contract disclaimer clauses on a road construction project; was lead attorney in multi-party litigation in Buffalo, New York involving performance and payment bond claims and default by a contractor; arbitrated disputes against municipalities concerning change orders and extra work on a highway construction project; successfully handled bid mistake/protest litigation, prevailing wage cases, mechanic’s lien matters, both public and private, and has successfully managed and defended claims against fidelity insurers involving coverage disputes.
Nell is an experienced advisor, litigator and negotiator in all types of construction and surety disputes and risk management situations. She is both editor and author for articles on cases, topics and trends significant to construction and surety professionals and businesses, including Ernstrom & Dreste, LLP’s quarterly newsletters, ContrACT: Construction Risk Management Reporter and Fidelity & Surety Reporter, available here.
Court Admissions:
- New York
- U.S. District Court, Western District of New York
- U.S. Bankruptcy Court, Western District of New York
Publications:
- “You Can’t Do That: Completion Without Notice Discharges Surety Under AIA A312,” NASBP Blog, July 2024, https://www.nasbp.org/blogs/kathryn-doran1/2024/07/18/you-cant-do-that-completion-without-notice-dischar
- “Town’s Notice of Withholding Triggers Claim Notice Requirements,” NASBP Blog, April 2024, https://www.nasbp.org/blogs/kathryn-doran1/2024/04/19/towns-notice-of-withholding-triggers-claim-notice.
- “Claims Handling Considerations for Select Contract Delivery Methods and Corresponding Contract and Bond Language,” co-author, paper submitted for program at ABA/TIPS Fidelity & Surety Law Committee Midwinter Conference, 2024
- “Unfit to Be Registered: The New DOL Contractor and Subcontractor Registration Law,” NASBP Blog, July 2023, https://www.nasbp.org/blogs/kathryn-doran1/2023/07/07/unfit-to-be-registered-the-new-dol-contractor-and
- “Contract’s ADR Term Not a Condition Precedent,” NASBP Blog, September 2023, https://www.nasbp.org/blogs/kathryn-doran1/2023/09/15/contracts-adr-term-not-a-condition-precedent
- “Refusing to Proceed with Changed Work Can Be Risky Business,” NASBP Blog, September 2022, https://www.nasbp.org/blogs/kat-shamapande/2022/09/28/refusing-to-proceed-with-changed-work-can-be-risky
- “Low Bidder, Or Not? Award on Base Bid Not Including Elected Alternate Violates Public Bidding Laws,” NASBP Blog, September 2022, https://www.nasbp.org/blogs/martha-perkins/2022/09/28/low-bidder-or-not-award-on-base-bid-not-including
- “Surety Discharged: Termination of Principal a Condition Precedent Under A312,” NASBP Blog, August 2021, https://www.nasbp.org/blogs/kathy-hoffman/2021/08/06/surety-discharged-termination-of-principal-a-condi
- “Miller Act Payment Bond: Federal Court Holds No-Damage-for-Delay Clause Unenforceable Against Subcontractor,” National Association of Surety Bond Producers Surety Bond Quarterly, vol.6, no. 3, Fall 2019
- “Design-Build Risks,” Chapter 2, Design-Build Risk and Insurance (Third Ed.), International Risk Management Institute, Inc., 2013, Co-Author
- “ConsensusDocs 310: Green Building Addendum,” Chapter 5, ConsensusDocs Contract Documents Handbook, Aspen Publishers, 2012, Author
Noteworthy Cases:
- Costanza Const. Corp. v. City of Rochester, 147 AD2d 929 (4th Dept 1989)
Professional Associations:
- American Bar Association
- Tort, Trial & Insurance Practice Section
- Fidelity & Surety Law Committee
- Forum on Construction Law
- Publications Committee
- Tort, Trial & Insurance Practice Section
Recognitions:
- Martindale.com; BV Distinguished Rating
- Super Lawyers; Upstate New York; Construction Litigation (2017-present)